some info on engine deliveries.
May 2 Porsche will address the list of vehicules under priority
May 5 engine ordering, don't ask me what this is I don't know. Maybe dealers have to place in the system the part ordereing
Week 19 delivery of engines
50% of engines will be delivered by week 20, that does not mean it will be installed but at least it will be delivered
All engines deliver by week 36, that is pretty long given the 50% residual quantities. So I guess the Category A, those who have already the cars will be sorted by end of May
Another good news, we will get 1 extra year of warranty plus the previously announced set of tirres and Frs 225
Overall, though this is frustrating, Porsche has provided a compeling indemnity.